The Laz-Scan Project. Who do you think should manage the Laz-skan development project?

Here are the candidates who might be considered to project manage the Laz-skan project. Obviously, this is going to be limited by the individuals who have been mentioned in the case. 

T.S. Lim, whose idea the Laz-skan project originally was.

Anuar Kamaruddin, the CEO of the Malaysian facility.

Bob Brierly, the Vice-President of development.

Halim Ramly, the Asian marketing Vice-President.

George Hudson, Head of Instrument Development

As an alternative to any of these, it has been suggested that bringing in an outside professional project manager may be the best solution.

Use the following matrix that displays the criteria as one dimension and the various candidates as the other. Mark the characteristics of each candidate using each criterion using a 0, 1, 2, or 3 star rating system. 

Answer:  The purpose of this process is to generate a debate about which characteristics are important for project management and the characteristics of each candidate. In practice, the discussion of what is important for any particular project will demonstrate how difficult selection is. Because this is a novel project generated by a relatively small part of the group, project skills and enthusiasm should probably rate highly. However, because it is also a very different project to ones that have been developed before, it may be that organizational influence is also very important. No single candidate has all of these qualities.

The business in fact came to the conclusion that T.S. Lim should be appointed as project manager but with very strict reporting relationship to Bob Brierly.